New contracts with Norsk Omipower

Energi Teknikk has signed contracts for delivery of electromechanical packages to Norsk Omipower. The Projects are Krossdalselvi powerplant and Brattabøelvi powerplant. The Projects are located in Jondal, in Ullensvang municipality in Norway.

Krossdalselvi powerplant will have an installed capacity of 5,8MW with a net head of 146 meters.

Brattabøelvi powerplant will have an installed capacity of 4,4MW with a net head of 239 meters.

Four new projects to Hywer

Energi Teknikk has signed contracts with Hywer for delivery of electromechanical supply to Tokheimselva-, Fossåa-, Rysna-, and Bergesåi powerplants. Småkraft AS is the project owner for these powerplants.

Tokheimselva powerplant is located in Ullensvang municipality in Norway, and will have an installed capacity of 8,4MW with a net head of 386 meters.

Fossåa powerplant is located in Vinstra municipality in Norway, and will have an installed capacity of 8,4MW with a net head of 405 meters.

Rysna powerplant is located in Vang municipality in Norway, and will have an installed capacity of 3,5MW with a net head of 136 meters.

Bergesåi powerplant is located in Fyresdal municipality in Norway, and will have an installed capacity of 3,7MW with a net head of 208 meters.

New contract – Valedalen powerplant

Energi Teknikk has signed the contract for the electromechanical supply to Valedalen powerplant. The customer is Valen kraftverk AS.

Valedalen powerplant is in Vestland in Norway. The powerplant will have an output of 1,15 MW with a head of 99,5 meters.  The turbine type is a vertical ET pelton turbine.  The powerplant will be put in operation in Q4 2020.

New contract – Nye Utvik powerplant

Energi Teknikk has signed the contract for the electromechanical supply to Nye Utvik powerplant. The customer is Utvik Elektrisitetsverk.

Nye Utvik powerplant is in Hordaland in Norway. The powerplant will have an output of 5,7 MW with a head of 252 meters.  The turbine type is a Brekke vertical pelton turbine.  The powerplant will be put in operation in Q4 2020.

Two new contracts with Captiva.

Energi Teknikk has signed the contract for the electromechanical supply to Markåni powerplant and Ytre Oppedal powerplant. The customer is Captiva.

Markåni powerplant is in Hordaland in Norway. The powerplant will have an output of 3,8 MW with a head of 310 meters.  The turbine type is a vertical pelton turbine.  The powerplant will be put in operation in Q3 2020.

Ytre Oppedal powerplant is in Hordaland in Norway. The powerplant will have an output of 3,5 MW with a head of 228 meters.  The turbine type is a vertical pelton turbine.  The powerplant will be put in operation in Q3 2020

Two new contracts with Småkraft Utbygging AS

Energi Teknikk has signed the contract for the electromechanical supply to Stampaelva powerplant and Fivelandselva powerplant. The owner is Småkraft Utbygging AS

Stampaelva powerplant is in Hordaland in Norway. The powerplant will have an output of 5,9 MW with a head of 541 meters.  The turbine type is a vertical pelton turbine.  The powerplant will be put in operation in Q4 2020

Fivelandselva powerplant is in Rogaland in Norway. The powerplant will have an output of 3,1 MW with a head of 234 meters.  The turbine type is a vertical pelton turbine.  The powerplant will be put in operation in Q4 2020

two new contracts with Clemens Kraft

Energi Teknikk has signed two new contracts with Clemens Kraft. Scope of supply is electromechanical supply.

Trollvikelva powerplant is located in Troms in Norway. The powerplant will have an output of 7,9 MW with a head of 388 meters.  The turbine type is a vertical Pelton turbine.  The powerplant will be put in operation in Q2 2020.

Salhuselva powerplant is located in Nordland in Norway. The powerplant will have an output of 3,4 MW with a head of 176 meters.  The turbine type is a vertical Pelton turbine.  The powerplant will be put in operation in Q2 2020.

 

New contract – Nottveit powerplant

Energi Teknikk has signed the contract for the electromechanical supply to Nottveit powerplant. The owner is Nottveit Energi AS.

The Power plant is located in Hordaland in Norway. The powerplant will have an output of 5,5 MW with a head of 279 meters.  The turbine type is a vertical pelton turbine.  The powerplant will be put in operation in Q2 2020